Work to begin on streets on west side of Idaho Falls
IDAHO FALLS, Idaho (KIFI) - On July 25, HK Contractors will begin work on several roads on the west side of Idaho Falls.
Construction activities include removal and replacement of existing ADA ramps and curbs at intersections, adjusting manholes and water vales, and placing asphalt overlays at the following locations:
- Vega Circle: cul-de-sac to N. Saturn Avenue
- Denver Street: Utah Avenue to before cul-de-sac
- Seattle Street: Lindsay Boulevard to N Utah Avenue
- Grandview Ct: Grandview Drive to cul-de-sac
- N Lindsay Boulevard: US 20 to north city limits
The work is currently scheduled to impact only a portion of the existing roadway at one time. Barring unforeseen conditions all properties will be accessible during construction. The anticipated completion time for all roads is two months.
Please reduce speeds, obey posted traffic control signage, and watch for construction crews throughout the work zone.
For questions or concerns about this project, contact HK Contractors at (208) 523-6600.