Sewer line replacements begin Tuesday
JM Concrete will be doing construction on various streets in Idaho Falls starting Tuesday.
Construction associated with the sewer line replacement project will start with Energy Drive, Shoup Avenue and N. Boulevard.
The anticipated completion date for those streets is Aug. 23, barring unforeseen conditions.
There will be modifications in traffic flow and/or alternate routes.
On Aug. 26, crews will move to Rollandet Street, between 17th Street and Sunnyside Road. The anticipated completion date for that section is Sept. 20, barring unforeseen conditions.
All homes and businesses in the construction area will remain accessible.