D Street underpass nears completion

The Idaho Falls Public Works Division now says construction work on the D Street underpass should be complete by mid-August.

The project began in March 2013, and the road has been closed between Yellowstone and Eastern Avenue ever since.

The underpass was originally scheduled for completion in June, but a Union Pacific train derailment outside the area pulled railroad crews off the project.According to the City of Idaho Falls, that caused delays in getting railroad traffic switched over to the new structure.

A railroad crossing at Lava Street will be permanently closed following completion of the D Street underpass.A pedestrian railroad crossing at B Street and Yellowstone Avenue is already open.

Article Topic Follows: News

Jump to comments ↓

Author Profile Photo

News Team

BE PART OF THE CONVERSATION

KIFI Local News 8 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content