Skip to Content

BPA rejects transmission line

NorthWestern Energy says it has been notified by the Bonneville Power Administration that BPA will not use a proposed $1 billion Mountain States Transmission Intertie to serve its southern Idaho loads.

BPA cited market uncertainties and environmental issues for its decision.

NorthWestern Energy said it may have to write off up to $24 million it has already spent on survey and investigating costs for the proposed 430-mile power line.

City of Idaho Falls spokesman Brad Huerta said the project was one of six options being considered by BPA to deliver power to Idaho Falls Power.

Huerta said BPA has instead decided to pursue the Gateway West project, designed to deliver Wyoming wind power to Idaho and other markets.

Article Topic Follows: News

Jump to comments ↓

Author Profile Photo

News Team

BE PART OF THE CONVERSATION

KIFI Local News 8 is committed to providing a forum for civil and constructive conversation.

Please keep your comments respectful and relevant. You can review our Community Guidelines by clicking here

If you would like to share a story idea, please submit it here.

Skip to content