Traffic shifts planned for WYO 22/WYO 390
JACKSON, Wyo. (KIFI) - The Wyoming Department of Transportation, along with contract crews from Ames Construction, will shift traffic at the Wyoming State Highway 22 intersection with Wyoming State Highway 390 beginning May 1 to allow crews to excavate and install the rest of the wildlife crossing box under WY0 390.
Crews will also be working to prepare and pour additional concrete pavement at the intersection. WYDOT does not anticipate significant delays but cautions drivers to travel slowly through the construction zone and pay attention to the adjusted traffic patterns.
Eastbound through-traffic on WYO 22 will remain in the new bypass lane. Eastbound WYO 22 traffic turning left onto WY0 390 will use an adjacent lane controlled by the signal.
Westbound traffic on WYO 22 will have access to the new free right turn lane before the light and will be shifted to the south side of the new signal pole. Southbound WY0 390 traffic traveling onto WYO 22 will be moved to the east but will still have dedicated left and right turn lanes.
Unpredictable weather and other variables may necessitate last-minute changes to the plans. WYDOT remains committed to updating the public with timely information. For more information about the current work going on at the WYO 22/WYO 390Â intersection and Snake River Bridge, click HERE.