17th Street construction continues
Now that paving on 17th Street from S Holmes Avenue to Woodruff Avenue is complete, construction crews will turn their focus to the next phase of the 17th Street Improvement project.
Over the next few weeks, crews will adjust manholes and water valves on the roadway, install median curb and seal coating.
The median curb work at intersections will impact traffic during construction as well as the allowed movements after the improvements are completed.
Final striping will occur after the seal coat, which is approximately one month from now.